The Energy (Amendment) Bill, 2023

1 Sep 2023 domainSenate Senate Bills No. 42 Gazette: Supplement No. 162
View original PDF

Status Timeline

Proposed

Active now

Public Review

Pending

Debate

Pending

Executive

Pending

Final

Pending

1

Beneficial Ownership Disclosure Made Mandatory

Energy purchase agreements can only be entered into with generating entities that have registered and disclosed their full beneficial ownership under the Companies Act (Act No. 17 of 2015). Purchasing entities must publish this register of beneficial ownership on their websites and in their annual audit reports within ninety days of the section's commencement.

2

Feasibility Studies Required Before Power Procurement

Before procuring electrical power, purchasing entities are mandated to conduct a feasibility study to identify whether there is sufficient local electricity demand that cannot be met by existing production. All procurement must comply with the Public Procurement and Asset Disposal Act (Act No. 33 of 2015).

3

Green Energy and Base Load Given Priority

Purchasing entities must structure energy purchase agreements to give priority to dispatchable generation with a sustainable base load at the point of dispatch, as well as to generating entities producing energy through renewable technologies.

4

Public Registry for Power Purchase Contracts

Purchasing entities must maintain a physical and digital registry of all active energy purchase agreements and their beneficial ownership. This register must be open to public inspection in accordance with Section 5(1)(e) of the Access to Information Act (Act No. 31 of 2016).

Comments (0)

No comments yet. Be the first to start the discussion!